Program Interconnection Standards
Category Regulatory Policy
Implementing sector State
Last Update
State Ohio
Website https://puco.ohio.gov/utilities/electricity/resources/interconnection-applicant…
Technologies Solar Thermal Electric, Solar Photovoltaics
Sectors Residential

Ohio most recently revised its interconnection rules in 2014.

Ohio's interconnection standards provide for three levels of review for the interconnection of DG systems up to 20 megawatts (MW) in capacity. 

All applicants are eligible but not required to request pre-application report that provides site-specific information. Interested applicants can choose to obtain this pre-application report at a cost (request procedure, timeline and cost are detailed in 4901:1-22-04(B)(2)).

Level 1 simplified review procedure allows eligible inverter-based distributed generators to have their interconnection request reviewed within 15 business days and a standard interconnection agreement within 5 business days of determination. Key eligibility requirements for this process include a nameplate capacity of 25 kilowatts or less and meeting IEEE 1547 and UL 1741 standards. Additional, site-specific eligibility requirements and approval criteria are listed in the rules.

Level 2 interconnection has expedited and supplemental review procedures that applies to certified, inverter-based or synchronous systems up to 5 MW in capacity. Specific capacity limits vary depending upon criteria at the proposed point of interconnection. These systems must meet IEEE 1547 and UL 1741 standards and may not be interconnected at the transmission level. Technical screens, fees, capacity-limit criteria, and timelines are detailed in the rules. Approved applicants will receive a standard interconnection agreement.

If the electric distribution utility determines that the applicant does not meet the approval criteria, the utility can:

  • allow the applicant to interconnect IF all safety, reliability, and power quality standards can be satisfactorily met;
  • determine that further study or minor modifications must occur before the facility can meet requirements to interconnect to be carried out by either the applicant or the utility;
  • obtain the applicant's agreement to continue evaluating the application under level 3 standard review;
  • begin a level 2 supplemental review process described in detail in the rules

Level 3 interconnection, the standard procedure, applies to inverter-based or synchronous systems up to 20 MW in capacity that do not qualify for Level 1 or Level 2 certification. Technical screens, fees and timelines are detailed in the rules.

The interconnection forms specify two application forms for interconnection: a "short form" application for systems up to 25 kW in capacity and utilize equipment that is certified in compliance with IEEE 1547 and UL1741, and a standard application for systems that do not qualify for the "short form" application. The PUCO website also provides a checklist for applicants to determine whether to complete the "short form" or the standard form.

Each utility must provide applicants with a standard interconnection agreement following completion of project review, and must designate an employee or office to provide the applicant with information on the requirements for the utilities’ application review process. Utilities may not require additional liability insurance beyond proof of insurance. The rules include a provision for alternative dispute resolution for non-residential and non-commercial customers, and for formal complaints brought by applicants and interconnected customers. Interconnection to area networks is generally permitted but is subject to review under the 3 level review framework.

Add new comment